Annual Town Street Resurfacing Expected to Begin this Week
The Town recently published a press release regarding the annual road resurfacing work. The News of Davidson team took the information in that release, which is published in full at the bottom of this article, and combined it with more detailed information that was available on the Town website.
The work can be binned into three categories: 1) crack and seal, 2) pavement repair / patching, and 3) milling and paving. The crack and seal work is the least complex, and the milling and paving the most complex.
Additionally, we took the map that was provided and transferred the information to several screenshots of Google maps to show a more detailed overview of where the work will take place. The crack and seal work is identified with yellow lines, the pavement repair with blue lines, and the milling and paving with red lines.
Most importantly, as the Town’s press release highlights, NO road closures are expected with the work. The contractor will close lanes as needed, but not full road closures. The work was scheduled to begin on September 16 and end on October 31. However, paving work is influenced by both rain and temperatures.
CRACK SEALING
Street Name Location of work
Caldwell Lane St. Albans to Conroy Avenue
Cloyd S. Goodrum Byway N. Faulkner Way to dead end
Conroy Ave Caldwell Lane to Wolfe Street
Fairview Lane Concord Road to N. Faulkner
Grey Road Concord Road to Wolfe Street
Harper Lee Street Conroy Avenue to O’Henry Avenue
N. Faulkner Way Conroy Avenue to Cloyd S. Goodrum Byway
S. Faulkner Way Conroy Avenue to Cloyd S. Goodrum Byway
St. Alban’s Lane Concord Road to Caldwell Lane
Wolfe Street Grey Road to O’Henry Avenue
PAVEMENT REPAIR, PATCHING
Street Name Location(s)
Ashby Drive 1 location
Churchill Road 10 locations
Clemens Place 1 location
Morrison Hill Road 4 locations
O’Henry Avenue 1 location
N. Kimberly Road 1 location
Westmoreland Farms Road 1 location at end of road
MILLING AND PAVING
Street Name Location of work
Bailey Springs Road Town limits to Robert Walker Drive
Bradford Park Drive Bailey Springs Drive to Robert Walker Drive
Hudson Place S. Kimberly Road to dead end
Mary E Gamble Byway St. Albans Lane to Caldwell Lane
N. Downing Street Concord Road to Ashby Drive
Lynbrook Drive Concord Road to Churchill Road
Lingle Drive Spencer Street to Ashby Drive
S. Kimberly Road Concord Road to North Downing Street
Robert Walker Drive Bailey Springs Drive to Trail/Greenway Crossing
S. Kimberly Road Concord Road to Hudson Place
Woody Lane S. Kimberly Road to dead end
Wallace M. Gamble Byway St. Albans Lane to Caldwell Lane
The full Town press release:
DAVIDSON, NC — As part of the annual streets resurfacing project, the Town of Davidson will be contracting road work starting Monday, September 16, 2024. This work serves as year four of a comprehensive five-year plan to maintain and improve streets throughout Davidson. The plan focuses on paving in tight geographic areas to be the most cost effective and will generally move west to east over the five years.
A pavement survey provides data to guide the decision-making process in terms of prioritization and the type of improvement needed on specific roadways. $600,000 of the Town of Davidson budget is allocated each year towards these paving related activities.
As shown on the map, streets that will see improvement this year are located within the “east central” region of Davidson including St. Albans, McConnell, South Kimberly, Bradford, and Westmoreland Road as of Monday, September 16, 2024.
Streets to receive maintenance include:
Ashby Drive
Bailey Springs Drive
Bradford Park Drive
Caldwell Lane
Churchill Road
Clemens Place
Cloyd S. Goodrum Byway
Conroy Alley (sic) Avenue
Fairview Lane
Grey Road
Harper Lee Street
Hudson Place
Lingle Drive
Lynbrook Drive
Mary E. Gamble Byway
Morrison Hill Road
N. Downing Street
N. Faulkner Way
N. Kimberly Road
O Henry Avenue
Robert Walker Drive
S. Faulkner Way
S. Kimberly Road
St. Albans Lane
Wallace M. Gamble Byway
Westmoreland Farm Rd
Wolfe Street
Woody Lane
The expected completion date is Friday, October 31, 2024, dependent upon weather.
There will be temporary lane closures for the project, but no road closures. We will work to minimize impact to affected residents.